Executive overview
Manchester City Yas Residences by Ohana
Yas Canal, Abu Dhabi · Contract value AED 1.18B · data date 01 Nov 2026
Illustrative demo data · data date 01 Nov 2026 · AED. KPIs are calculated live from the editable project records.
SPI
0.93
EV 58.4% vs PV 63.1%
CPI
0.95
EAC AED 1.24B
Schedule checks
0/11
3 not assessed
Negative float
9
incomplete tasks
Risk EMV
AED31.6M
65 days · 2 high
Peak funding gap
AED65.8M
Mar 2027
Verified progress
58.8%
reported 95.7% (BOQ)
Open actions
0
0 overdue
AI analysis
No AI analysis yet for this project. Deterministic results are shown; click What needs attention this week? to analyse the current project data.
Earned value trend (cumulative)
PV from baseline dates, EV from activity % complete × budget, AC from monthly cost ledger ratio. Last point recalculated live.
Schedule health (DCMA-style)
Bar = % of check denominator affected (check 04 shows % non-FS). Orange = fails threshold.
Cashflow — cumulative position
Top concerns (computed signals)
- Forecast funding gap AED 65,816,000 in 2027-03CashflowAED 65.8M
- 1 payment(s) overdue — AED 37,214,320PaymentAED 37.2M
- Reported progress exceeds verified by 37.0 ptsProgressAED 9.4M
- Negative float on 10 activities (worst -24d)ScheduleAED 2.8M24d
- MCY-CO-002: Deadline passed — no noticeContractual noticeAED 1.5M18d
- MCY-CO-003: Due in 2 daysContractual noticeAED 1.1M24d